LOCKOUT/TAGOUT CHECKLIST
LOCKOUT/TAGOUT CHECKLIST
Prior to beginning work on machinery, equipment, or systems requiring Lockout/Tagout, check each item. If there are items that are not applicable to the entry, mark them "N/A".
Job Site:
Date:
Time:
Foreman:
Exp. Date:
Exp. Time:
PERSONAL PROTECTIVE EQUIPMENT
- Hard Hat
- Eye/Face Protection (type)
- Protective clothing (type)
- Gloves (type)
- Respirator (type)
- Fall protection / Other
SHUTDOWN & LOCKOUT
- Electrical lockout/tagout completed
- Valves closed, lockout/tagout completed
- Lines blinded/blocked off
- Lines disconnected
- Line bleeders open
- All hydraulic/pneumatic pressure released
- All other energy released and/or guarded (magnetic, spring, gravity, reactivity)
- Hot work permit completed
- System/area check for flammables/vapors
- Fire extinguisher on site/in area
- Barricade/Exclusion Zone markers in place
- Machine/Equipment/System users / other personnel notified
REACTIVATION
- Electrical/System reconnected
- Line blinds/block-offs removed
- Line breeders closed
- Guards reinstalled
- Tools/materials removed
- Machine/Equipment/System users / other personnel clear and safe
- Electrical lockout/tagout removed
- Valve(s) lockout/tagout removed
WORK TEAM
Print Initial
Foreman
Safety
Customer
JOB COMPLETED
Date:
Time: