START-UP SHEET Hydronic Piping
Job Name ____ Job Number ____
Job Address ____
Section 5: Equipment Description
| Spec. #: | Submittal #: | P&ID/Dwg #: |
|---|---|---|
| Area Served: |
Service Type: Chilled Water Process Water
Heating Water Other: Condenser Water
Section 6: Equipment Pre-Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 6.2 | Nameplate data matches vendor specifications. | □ | □ | □ | |
| 6.3 | All parts are received. | □ | □ | □ | |
| 6.4 | No visible signs of damage, leak, or defective parts. | □ | □ | □ | |
| 6.5 | Operational and Maintenance(O&M) manual is available in the field. | □ | □ | □ | |
| 6.6 | Start-up technicians reviewed factory start-up procedures in the O&M manual. | □ | □ | □ |
Section 7: Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 7.2 | Piping is per specifications. | □ | □ | □ | |
| 7.3 | Piping is labeled per specifications. | □ | □ | □ | |
| 7.4 | Piping is installed level or to specifications. | □ | □ | □ | |
| 7.5 | Piping is insulated per specifications. | □ | □ | □ | |
| 7.6 | Piping is supported per specifications. | □ | □ | □ |
Comments/ Observations
Performed By (Therma)
Reviewed By (Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 7.7 | Piping is seismically restrained per specifications. | □ | □ | □ | |
| 7.8 | Piping materials are per specifications. | □ | □ | □ | |
| 7.9 | Piping of dissimilar materials has dielectric isolation per specifications. | □ | □ | □ | |
| 7.10 | Piping has proper drains per specifications. | □ | □ | □ | |
| 7.11 | Piping has proper vents per specifications. | □ | □ | □ | |
| 7.12 | Piping has branch isolation valves per specifications. | □ | □ | □ | |
| 7.13 | Piping has main isolation valves per specifications. | □ | □ | □ | |
| 7.14 | Piping has undergone a hydrostatic pressure test per specifications. | □ | □ | □ | |
| 7.15 | Piping has make up water regulator valve per specifications. | □ | □ | □ | |
| 7.16 | Piping has fast fill regulator bypass per specifications. | □ | □ | □ | |
| 7.17 | Piping has pressure relief valve per specifications. | □ | □ | □ | |
| 7.18 | Pressure relief valve and vents are piped to relieve to an area specified. | □ | □ | □ | |
| 7.19 | Piping is full of water. | □ | □ | □ | |
| 7.20 | Piping is vented of air. | □ | □ | □ | |
| 7.21 | Pressure and temperature gauges are installed per specifications. | □ | □ | □ | |
| 7.22 | Piping has chemical pot feeder per specifications. | □ | □ | □ | |
| 7.23 | Chemical pot feeder is installed per specifications. | □ | □ | □ | |
| 7.24 | Chemical feed system is installed per specifications. | □ | □ | □ |
Comments/ Observations
| Print Name | Signature | Date |
|---|---|---|
Section 8: Operational Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 8.2 | Open all isolation bypass and controls valves. | □ | □ | □ | |
| 8.3 | Set make up water pressure regulator valve to operating pressure setting per specifications. | □ | □ | □ | |
| 8.4 | Open fast fill regulator to test pressure relief. | □ | □ | □ | |
| 8.5 | Drain pressure to operating pressure setting. | □ | □ | □ | |
| 8.6 | Start-up pumps (use start-up sheet FN 8.033.1) | □ | □ | □ | |
| 8.7 | Piping vibration is acceptable. | □ | □ | □ | |
| 8.8 | Inspect all piping for leaks and repair as needed. | □ | □ | □ | |
| 8.9 | Restart pumps. | □ | □ | □ | |
| 8.10 | Scrub piping with soap per specifications. | □ | □ | □ | |
| 8.11 | When scrub is complete open drain valve to sanitary drain (be sure make up regulator or fast fill is open) maintain system pressure while draining. | □ | □ | □ | |
| 8.12 | Clean all strainers clear all blowdowns. | □ | □ | □ | |
| 8.13 | Check make up water P.H. and T.D.S. | □ | □ | □ | |
| 8.14 | Compare make up water P.H. and T.D.S. readings to pipe system readings. | □ | □ | □ | |
| 8.15 | Add water treatment per specifications. | □ | □ | □ | |
| 8.16 | Start-up chemical feed system per specifications and manufacturers recommendations. | □ | □ | □ |
Comments/ Observations
| Print Name | Signature | Date |
|---|---|---|
START-UP SHEET Hydronic Piping
Water Treatment Use
| Water Treatment Used | Amount | Initial Levels |
|---|---|---|
End of Section
Comments/ Observations
Comments/ ____
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|