8 046 1 start up sheet hydronic piping

START-UP SHEET Hydronic Piping

Job Name ____ Job Number ____

Job Address ____

Section 5: Equipment Description

Spec. #: Submittal #: P&ID/Dwg #:
Area Served:

Service Type: Chilled Water Process Water

Heating Water Other: Condenser Water

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.2 Nameplate data matches vendor specifications. □ □ □
6.3 All parts are received. □ □ □
6.4 No visible signs of damage, leak, or defective parts. □ □ □
6.5 Operational and Maintenance(O&M) manual is available in the field. □ □ □
6.6 Start-up technicians reviewed factory start-up procedures in the O&M manual. □ □ □

Section 7: Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.2 Piping is per specifications. □ □ □
7.3 Piping is labeled per specifications. □ □ □
7.4 Piping is installed level or to specifications. □ □ □
7.5 Piping is insulated per specifications. □ □ □
7.6 Piping is supported per specifications. □ □ □

Comments/ Observations

Performed By (Therma)

Reviewed By (Owner/Representatives)

Print Name Signature Date

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.7 Piping is seismically restrained per specifications. □ □ □
7.8 Piping materials are per specifications. □ □ □
7.9 Piping of dissimilar materials has dielectric isolation per specifications. □ □ □
7.10 Piping has proper drains per specifications. □ □ □
7.11 Piping has proper vents per specifications. □ □ □
7.12 Piping has branch isolation valves per specifications. □ □ □
7.13 Piping has main isolation valves per specifications. □ □ □
7.14 Piping has undergone a hydrostatic pressure test per specifications. □ □ □
7.15 Piping has make up water regulator valve per specifications. □ □ □
7.16 Piping has fast fill regulator bypass per specifications. □ □ □
7.17 Piping has pressure relief valve per specifications. □ □ □
7.18 Pressure relief valve and vents are piped to relieve to an area specified. □ □ □
7.19 Piping is full of water. □ □ □
7.20 Piping is vented of air. □ □ □
7.21 Pressure and temperature gauges are installed per specifications. □ □ □
7.22 Piping has chemical pot feeder per specifications. □ □ □
7.23 Chemical pot feeder is installed per specifications. □ □ □
7.24 Chemical feed system is installed per specifications. □ □ □

Comments/ Observations

Print Name Signature Date

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By (Initials & Date)
8.2 Open all isolation bypass and controls valves. □ □ □
8.3 Set make up water pressure regulator valve to operating pressure setting per specifications. □ □ □
8.4 Open fast fill regulator to test pressure relief. □ □ □
8.5 Drain pressure to operating pressure setting. □ □ □
8.6 Start-up pumps (use start-up sheet FN 8.033.1) □ □ □
8.7 Piping vibration is acceptable. □ □ □
8.8 Inspect all piping for leaks and repair as needed. □ □ □
8.9 Restart pumps. □ □ □
8.10 Scrub piping with soap per specifications. □ □ □
8.11 When scrub is complete open drain valve to sanitary drain (be sure make up regulator or fast fill is open) maintain system pressure while draining. □ □ □
8.12 Clean all strainers clear all blowdowns. □ □ □
8.13 Check make up water P.H. and T.D.S. □ □ □
8.14 Compare make up water P.H. and T.D.S. readings to pipe system readings. □ □ □
8.15 Add water treatment per specifications. □ □ □
8.16 Start-up chemical feed system per specifications and manufacturers recommendations. □ □ □

Comments/ Observations

Print Name Signature Date

START-UP SHEET Hydronic Piping

Water Treatment Use

Water Treatment Used Amount Initial Levels

End of Section

Comments/ Observations

Comments/ ____

Performed By

(Therma)

Reviewed By

(Owner/Representatives)

Print Name Signature Date