8 045 1 start up sheet cooling tower
START-UP SHEET Cooling Tower
Job Name ____ Job Number ____
Job Address ____
Section 5: Equipment Description
| Spec. #: | Submittal #: | P&ID/Dwg #: |
|---|---|---|
| Area Served: |
| Data | Design | Actual On Site |
|---|---|---|
| Unit Tag # | ||
| Manufacturer | ||
| Model # | ||
| Serial # | ||
| Tower Fan Motor Manufacturer | ||
| Model # | ||
| Serial # | ||
| Tower Pump Motor Manufacturer | ||
| Model # | ||
| Serial # | ||
| Belts | ||
| Belts |
Section 6: Equipment Pre-Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 6.2 | Nameplate data matches vendor specifications. | □ | □ | □ | |
| 6.3 | All parts are received. | □ | □ | □ | |
| 6.4 | No visible signs of damage, leak, or defective parts. | □ | □ | □ |
Comments/ ____
Observations
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection. | □ | □ | □ | |
| 6.6 | Operational and Maintenance(O&M) manual is available in the field. | □ | □ | □ | |
| 6.7 | Start-up technicians have reviewed factory start-up procedures in the O&M manual. | □ | □ | □ | |
| 6.8 | If Therma provided Variable Frequency Drives(VFDs) that are controlling fans and pumps, complete manufacturer's VFD start up forms. |
Section 7: Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 7.2 | Unit is installed level. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.3 | Tag # is attached to the unit. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.4 | Service clearance is adequate for maintenance. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.5 | Inlet air screens, fans, eliminators, heat exchanger sections,and sump strainers are installed and clean. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.6 | Shipping blocks and materials are removed from fan section. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.7 | Water sump is clean. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.8 | Water treatment is provided. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.9 | Sheaves are aligned. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.10 | Multi speed motor is installed. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.11 | Fan hub,sheaves and bearing setscrews are tight. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 7.12 | Each fan belt tension is correct. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ |
Comments/
Observations
Performed By (Therma)
Reviewed By (Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
| 7.13 | Motor and blower bearings are lubricated. | □ |
| 7.14 | Spray nozzles and water level controls are installed. | □ |
| 7.15 | Fan shaft bearing angular alignment is correct and bolts are tight. | □ |
| 7.16 | Vibration isolators are installed and adjusted. | □ |
| 7.17 | All electrical connections are secure. | □ |
| 7.18 | All access panels and covers are in place. | □ |
| 7.19 | Isolation valves are installed. | □ |
Section 8: Operational Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 8.2 | Unit vibration is acceptable. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.3 | Each fan rotation is correct. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.4 | Each pump rotation is correct. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.5 | Water level make-up valve is operating correctly. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.6 | Check tower for leaks. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.7 | Coupling assembly needs alignment. | $ extbackslash{Box}$ | $ extbackslash{Box}$ | $ extbackslash{Box}$ | |
| 8.8 | Record final data. | ||||
| 8.9 | Add water treatment per specifications. | ||||
| 8.10 | Record start up operating parameters below(If multiple components,including fans and pumps are part of the unit,record those information in the Supplementary Form,FN-8.028.2 or FN-8.028.3). |
Comments/ Observations
Performed By
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
START-UP SHEET Cooling Tower
Record Start Up Operating Parameters
| Data | Design | Actual On Site |
|---|---|---|
| Tower Inlet Temperature | ||
| Tower Outlet Temperature |
Water Treatment Use
| Water Treatment Used | Amount | Initial Levels |
|---|---|---|
End of Section
Comments/ Observations
Performed By
(Therma)
Reviewed By
| Print Name | Signature | Date |
|---|---|---|
(Owner/Representatives)