START-UP SHEET Electric Humidifier

Job Name ____ Job Number ____

Job Address ____

Section 5: Equipment Description

Spec. #: Submittal #: P&ID/Dwg #:
Area Served:

Service Type: DI Water $ \Box $ Steam $ \Box $ Other: ____

Data Design Actual On Site
Unit Tag #
Manufacturer
Model #
Serial #

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.2 Nameplate data matches vendor specifications $\Box$ $\Box$ $\Box$
6.3 All parts are received $\Box$ $\Box$ $\Box$
6.4 No visible signs of damage, leak, or defective parts $\Box$ $\Box$ $\Box$
6.5 Verify electrical service for correct voltage, current and thermal overload protection $\Box$ $\Box$ $\Box$
6.6 Operational and Maintenance(O&M) manual is available in field. $\Box$ $\Box$ $\Box$
6.7 Start-up technicians have reviewed factory start-up procedures in O&M manual. $\Box$ $\Box$ $\Box$

Comments/ Observations _____


Performed By

(Therma)

Reviewed By

(Owner/Representatives)

Print Name Signature Date

Section 7: Installation Inspection

ID Inspection Description Yes No N/A Performed By (Initials & Date)
7.2 Unit is installed in approved room and properly protected from weather and drafts. □ □ □
7.3 Unit is installed level on a concrete floor or non-combustible base. □ □ □
7.4 Tag # is attached to the unit. □ □ □
7.5 Service clearance is adequate for maintenance. □ □ □
7.6 Proper earth ground is connected to green ground screw in panel. □ □ □
7.7 Relief valve type, setting, and capacity are correct. □ □ □
7.8 System has been cleaned and treated. □ □ □
7.9 Make-up water supply make-up has proper shut-off and back flow device. □ □ □
7.10 Drain valve is installed. □ □ □
7.11 Temperature and pressure gauges are installed. □ □ □
7.12 High limit and operating controls are installed. □ □ □
7.13 Tube surfaces are inspected. □ □ □
7.14 Make-up water pressure regulator is installed. □ □ □

Comments/ Observations

Print Name Signature Date

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
8.2 Unit vibration is acceptable. □ □ □
8.3 Heating components perform per manufacturer's specification. □ □ □
8.4 Control is sequencing and modulating humidification properly. □ □ □
8.5 Record start up operating parameters.
Delta Design Actual
Delta Design Section 1 Section 2 Section 3 Section 4
Voltage
Current
Phase
Delta Design Actual
Delta Design Section 5 Section 6 Section 7 Section 8
Voltage
Current
Phase

END OF SECTION

Comments/ Observations

Performed By

(Therma)

Reviewed By

(Owner/Representatives)

Print Name Signature Date