8 043 1 start up sheet electric humidifier
START-UP SHEET Electric Humidifier
Job Name ____ Job Number ____
Job Address ____
Section 5: Equipment Description
| Spec. #: | Submittal #: | P&ID/Dwg #: |
|---|---|---|
| Area Served: |
Service Type: DI Water $ \Box $ Steam $ \Box $ Other: ____
| Data | Design | Actual On Site |
|---|---|---|
| Unit Tag # | ||
| Manufacturer | ||
| Model # | ||
| Serial # |
Section 6: Equipment Pre-Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 6.2 | Nameplate data matches vendor specifications | $\Box$ | $\Box$ | $\Box$ | |
| 6.3 | All parts are received | $\Box$ | $\Box$ | $\Box$ | |
| 6.4 | No visible signs of damage, leak, or defective parts | $\Box$ | $\Box$ | $\Box$ | |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection | $\Box$ | $\Box$ | $\Box$ | |
| 6.6 | Operational and Maintenance(O&M) manual is available in field. | $\Box$ | $\Box$ | $\Box$ | |
| 6.7 | Start-up technicians have reviewed factory start-up procedures in O&M manual. | $\Box$ | $\Box$ | $\Box$ |
Comments/ Observations _____
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
Section 7: Installation Inspection
| ID | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 7.2 | Unit is installed in approved room and properly protected from weather and drafts. | □ | □ | □ | |
| 7.3 | Unit is installed level on a concrete floor or non-combustible base. | □ | □ | □ | |
| 7.4 | Tag # is attached to the unit. | □ | □ | □ | |
| 7.5 | Service clearance is adequate for maintenance. | □ | □ | □ | |
| 7.6 | Proper earth ground is connected to green ground screw in panel. | □ | □ | □ | |
| 7.7 | Relief valve type, setting, and capacity are correct. | □ | □ | □ | |
| 7.8 | System has been cleaned and treated. | □ | □ | □ | |
| 7.9 | Make-up water supply make-up has proper shut-off and back flow device. | □ | □ | □ | |
| 7.10 | Drain valve is installed. | □ | □ | □ | |
| 7.11 | Temperature and pressure gauges are installed. | □ | □ | □ | |
| 7.12 | High limit and operating controls are installed. | □ | □ | □ | |
| 7.13 | Tube surfaces are inspected. | □ | □ | □ | |
| 7.14 | Make-up water pressure regulator is installed. | □ | □ | □ |
Comments/ Observations
| Print Name | Signature | Date |
|---|---|---|
Section 8: Operational Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 8.2 | Unit vibration is acceptable. | □ | □ | □ | |
| 8.3 | Heating components perform per manufacturer's specification. | □ | □ | □ | |
| 8.4 | Control is sequencing and modulating humidification properly. | □ | □ | □ | |
| 8.5 | Record start up operating parameters. |
| Delta | Design | Actual | |||
|---|---|---|---|---|---|
| Delta | Design | Section 1 | Section 2 | Section 3 | Section 4 |
| Voltage | |||||
| Current | |||||
| Phase |
| Delta | Design | Actual | |||
|---|---|---|---|---|---|
| Delta | Design | Section 5 | Section 6 | Section 7 | Section 8 |
| Voltage | |||||
| Current | |||||
| Phase |
END OF SECTION
Comments/ Observations
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|