# START-UP SHEET Chiller

Job Name ____ Job Number ____.  
Job Address ____

## Section 5: Equipment Description

| Spec. #: | Submittal #: | P&ID/Dwg #: |
| --- | --- | --- |
| Area Served: |  |  |

Chiller Type: Reciprocating Rotary Screw Centrifugal Other:

| Data | Design | Actual On Site |
| --- | --- | --- |
| Unit Tag # |  |  |
| Manufacturer |  |  |
| Model # |  |  |
| Serial # |  |  |

## Section 6: Equipment Pre-Installation Inspection

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
| --- | --- | --- | --- | --- | --- |
| 6.2 | Nameplate data matches vendor specifications. | ☐ | ☐ | ☐ |  |
| 6.3 | All parts are received. | ☐ | ☐ | ☐ |  |
| 6.4 | No visible signs of damage, leak, or defective parts. | ☐ | ☐ | ☐ |  |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection. | ☐ | ☐ | ☐ |  |
| 6.6 | Operational and Maintenance(O&M) manual is available in the field. | ☐ | ☐ | ☐ |  |
| 6.7 | Start-up technicians reviewed factory start-up procedures in the O&M manual. | ☐ | ☐ | ☐ |  |

Comments/ ____  
Observations  
observations _____

(Therma)

Performed By  
Reviewed By

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

(Owner/Representatives)

---

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
| --- | --- | --- | --- | --- | --- |
| 6.8 | If Therma provided Variable Frequency Drives(VFDs) that are controlling the fans, complete FN 8.029.1 VFD start-up form. |  |  |  |  |

## Section 7: Installation Inspection

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
| --- | --- | --- | --- | --- | --- |
| 7.2 | Unit is installed on flat foundation and level. | □ | □ | □ |  |
| 7.3 | Tag # is attached to the unit. | □ | □ | □ |  |
| 7.4 | Service clearance is adequate for maintenance. | □ | □ | □ |  |
| 7.5 | Controls are installed and tested. | □ | □ | □ |  |
| 7.6 | Valves are installed at inlet and outlet of evaporator and condenser water piping. | □ | □ | □ |  |
| 7.7 | Flow switches are installed in the chilled water and condenser water piping. | □ | □ | □ |  |
| 7.8 | Flow switches are set for minimum flow plus 10% | □ | □ | □ |  |
| 7.9 | Pressure and temperature test ports are installed at inlet and outlet of the evaporator and condenser. | □ | □ | □ |  |
| 7.10 | Drain valves are installed to the evaporator and condenser. | □ | □ | □ |  |
| 7.11 | Vent valves are installed on the top of the evaporator and condenser. | □ | □ | □ |  |
| 7.12 | Water regulating valve is installed. | □ | □ | □ |  |
| 7.13 | Water treatment is provided. | □ | □ | □ |  |

(Owner/Representatives)

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |
| 7.14 | Water pressure relief valves are installed in the evaporator and condenser water piping. | □ | □ | □ |  |
| 7.15 | All condenser fan setscrews are tight. | □ | □ | □ |  |
| 7.16 | Electrical connections are secure. | □ | □ | □ |  |
| 7.17 | All access panels and covers are in place. | □ | □ | □ |  |
| 7.18 | Vibration isolators are installed and adjusted. | □ | □ | □ |  |
| 7.19 | All compressor shipping braces and compressor rail isolator sleeves are removed. | □ | □ | □ |  |
| 7.20 | Coils are clean and fins are straight. | □ | □ | □ |  |
| 7.21 | Crankcase heaters are installed. | □ | □ | □ |  |
| 7.22 | Compressor oil level is within manufacturer's specification. | □ | □ | □ |  |
| 7.23 | Low ambient control is installed. | □ | □ | □ |  |
| 7.24 | Relief valve type, setting, and capacity are correct. | □ | □ | □ |  |
| 7.25 | Chilled&condenser water supply outlet is proper size. | □ | □ | □ |  |
| 7.26 | Chilled&condenser water return inlet is proper size. | □ | □ | □ |  |
| 7.27 | Make-up water supply has proper shut-off and back flow device. | □ | □ | □ |  |
| 7.28 | Temperature and pressure gauges are installed. | □ | □ | □ |  |
| 7.29 | Make-up water pressure regulator is installed. | □ | □ | □ |  |
| 7.30 | Expansion tank is installed. | □ | □ | □ |  |
| 7.31 | Pressure&temperature test ports are provided. | □ | □ | □ |  |

Comm Obser  
ments/  
vations

Performed By (Therma)

Reviewed By (Owner/Representatives)

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

---

# START-UP SHEET Chiller

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
| --- | --- | --- | --- | --- | --- |
| 7.32 | Air separation device is properly installed. | ☐ | ☐ | ☐ |  |
| 7.33 | Pump(s) are installed. | ☐ | ☐ | ☐ |  |
| 7.34 | Pot feeder is installed. | ☐ | ☐ | ☐ |  |
| 7.35 | System has been cleaned and treated. | ☐ | ☐ | ☐ |  |
| 7.36 | Isolation valves are installed. | ☐ | ☐ | ☐ |  |
| 7.37 | Water treatment is installed. | ☐ | ☐ | ☐ |  |

## Section 8: Operational Inspection

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
| --- | --- | --- | --- | --- | --- |
| 8.2 | Unit vibration is acceptable. | ☐ | ☐ | ☐ |  |
| 8.3 | Each fan rotation is correct. | ☐ | ☐ | ☐ |  |
| 8.4 | Cooling components perform per manufacturer's specifications. | ☐ | ☐ | ☐ |  |
| 8.5 | Crankcase heaters are functional. | ☐ | ☐ | ☐ |  |
| 8.6 | Make sure thermostat is set. | ☐ | ☐ | ☐ |  |
| 8.7 | Record start up operating parameters below then use Supplementary Forms (FN8.028.2 or FN8.028.3) for additional data. |  |  |  |  |

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

---

# START-UP SHEET Chiller

Record Start Up Operating Parameters

| Data | Design | Actual On Site |
| --- | --- | --- |
| Evaporator Pressure Drop |  |  |
| Evaporate Flow (GPM) |  |  |
| Data | Design | Actual On Site |
| Condenser Pressure Drop |  |  |
| Condenser Flow(GPM) |  |  |
| Chilled Water ΔT |  |  |

END OF SECTION

Comments/Observations

Performed (Therma)

By

Reviewed By

(Owner/Representatives)

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |