8 039 1 start up sheet chiller

START-UP SHEET Chiller

Job Name ____ Job Number ____.
Job Address ____

Section 5: Equipment Description

Spec. #: Submittal #: P&ID/Dwg #:
Area Served:

Chiller Type: Reciprocating Rotary Screw Centrifugal Other:

Data Design Actual On Site
Unit Tag #
Manufacturer
Model #
Serial #

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.2 Nameplate data matches vendor specifications. ☐ ☐ ☐
6.3 All parts are received. ☐ ☐ ☐
6.4 No visible signs of damage, leak, or defective parts. ☐ ☐ ☐
6.5 Verify electrical service for correct voltage, current and thermal overload protection. ☐ ☐ ☐
6.6 Operational and Maintenance(O&M) manual is available in the field. ☐ ☐ ☐
6.7 Start-up technicians reviewed factory start-up procedures in the O&M manual. ☐ ☐ ☐

Comments/ ____
Observations
observations _____

(Therma)

Performed By
Reviewed By

Print Name Signature Date

(Owner/Representatives)


Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.8 If Therma provided Variable Frequency Drives(VFDs) that are controlling the fans, complete FN 8.029.1 VFD start-up form.

Section 7: Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.2 Unit is installed on flat foundation and level. □ □ □
7.3 Tag # is attached to the unit. □ □ □
7.4 Service clearance is adequate for maintenance. □ □ □
7.5 Controls are installed and tested. □ □ □
7.6 Valves are installed at inlet and outlet of evaporator and condenser water piping. □ □ □
7.7 Flow switches are installed in the chilled water and condenser water piping. □ □ □
7.8 Flow switches are set for minimum flow plus 10% □ □ □
7.9 Pressure and temperature test ports are installed at inlet and outlet of the evaporator and condenser. □ □ □
7.10 Drain valves are installed to the evaporator and condenser. □ □ □
7.11 Vent valves are installed on the top of the evaporator and condenser. □ □ □
7.12 Water regulating valve is installed. □ □ □
7.13 Water treatment is provided. □ □ □

(Owner/Representatives)

Print Name Signature Date
7.14 Water pressure relief valves are installed in the evaporator and condenser water piping. □
7.15 All condenser fan setscrews are tight. □
7.16 Electrical connections are secure. □
7.17 All access panels and covers are in place. □
7.18 Vibration isolators are installed and adjusted. □
7.19 All compressor shipping braces and compressor rail isolator sleeves are removed. □
7.20 Coils are clean and fins are straight. □
7.21 Crankcase heaters are installed. □
7.22 Compressor oil level is within manufacturer's specification. □
7.23 Low ambient control is installed. □
7.24 Relief valve type, setting, and capacity are correct. □
7.25 Chilled&condenser water supply outlet is proper size. □
7.26 Chilled&condenser water return inlet is proper size. □
7.27 Make-up water supply has proper shut-off and back flow device. □
7.28 Temperature and pressure gauges are installed. □
7.29 Make-up water pressure regulator is installed. □
7.30 Expansion tank is installed. □
7.31 Pressure&temperature test ports are provided. □

Comm Obser
ments/
vations

Performed By (Therma)

Reviewed By (Owner/Representatives)

Print Name Signature Date

START-UP SHEET Chiller

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.32 Air separation device is properly installed. ☐ ☐ ☐
7.33 Pump(s) are installed. ☐ ☐ ☐
7.34 Pot feeder is installed. ☐ ☐ ☐
7.35 System has been cleaned and treated. ☐ ☐ ☐
7.36 Isolation valves are installed. ☐ ☐ ☐
7.37 Water treatment is installed. ☐ ☐ ☐

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
8.2 Unit vibration is acceptable. ☐ ☐ ☐
8.3 Each fan rotation is correct. ☐ ☐ ☐
8.4 Cooling components perform per manufacturer's specifications. ☐ ☐ ☐
8.5 Crankcase heaters are functional. ☐ ☐ ☐
8.6 Make sure thermostat is set. ☐ ☐ ☐
8.7 Record start up operating parameters below then use Supplementary Forms (FN8.028.2 or FN8.028.3) for additional data.
Print Name Signature Date

START-UP SHEET Chiller

Record Start Up Operating Parameters

Data Design Actual On Site
Evaporator Pressure Drop
Evaporate Flow (GPM)
Data Design Actual On Site
Condenser Pressure Drop
Condenser Flow(GPM)
Chilled Water ΔT

END OF SECTION

Comments/Observations

Performed (Therma)

By

Reviewed By

(Owner/Representatives)

Print Name Signature Date