8 037 1 start up sheet coils

START-UP SHEET Coils

Job Name ____

Job Number ____

Job Address

Section 5: Equipment Description

Spec. #: Submittal #: P&ID/Dwg #:
Area Served:
Step Unit Tag # Section 6: Pre-Installation Inspection
62 Nameplate data matches vendor specifications.
63 All parts are received.
64 No visible signs of damage, leak, or defective parts.
65 Connections: size & location match specification.
66 Operational and Maintenance (O&M) manual is available in the field.
67 Start-up technician reviewed factory start-up procedures in the O&M manual.

Performed By: Print Name ____ Initials ____ Date ____

Section 6: Installation Inspection

7.2 Unit is properly installed per design.
7.3 Tag # is attached to the unit.
7.4 Service clearance is adequate for maintenance.
7.5 Ductwork and flex connections are connected and sealed.
7.6 Connection between the unit and piping are installed per good piping practices.
7.7 Isolation valves are installed.
7.8 In-line strainer is installed.
7.9 Coil drain valve is installed.
7.10 Condensate drain is trapped.
7.11 Pressure and temperature test ports are installed.
7.12 Air bleed devices are installed.
7.13 Control valve is installed.
7.14 Balancing devices are installed.
7.15 Pressure relief devices are installed.
7.16 Electrical connections are secure.

Performed By: Print Name ____
Reviewed By: Print Name ____
Initials _____
Initials ____

Note: Use " $ \surd $ " = Yes, " X " = No or " 0 " = Not Applicable

Date _____

Date ____