8 036 1 start up sheet boiler
UP SHEET oiler
Job Name ____
Job Number ____
Job Address ____
Section 5: Equipment Description
| Spec. #: | Submittal #: | P&ID/Dwg #: |
|---|---|---|
| Area Served: |
Service Type: Hot Water $ \Box $ Steam $ \Box $ Other: $ \Box $ _____
| Data | Design | Actual On Site |
|---|---|---|
| Unit Tag # | ||
| Manufacturer | ||
| Model # | ||
| Serial # |
Section 6: Equipment Pre-Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 6.2 | Nameplate data matches vendor specifications | $\Box$ | $\Box$ | $\Box$ | |
| 6.3 | All parts are received | $\Box$ | $\Box$ | $\Box$ | |
| 6.4 | No visible signs of damage, leak, or defective parts | $\Box$ | $\Box$ | $\Box$ | |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection | $\Box$ | $\Box$ | $\Box$ | |
| 6.6 | Operational and Maintenance(O&M) manual is available in field. | $\Box$ | $\Box$ | $\Box$ | |
| 6.7 | Start-up technicians have reviewed factory start-up procedures in O&M manual. | $\Box$ | $\Box$ | $\Box$ |
Comments/Observations
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
START-UP SHEET Boiler
Section 7: Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 7.2 | Unit is installed in approved room and properly protected from weather and drafts. | □ | □ | □ | |
| 7.3 | No negative pressure in the approved room. | □ | □ | □ | |
| 7.4 | Proper air openings are provided. | □ | □ | □ | |
| 7.5 | Unit is installed level on a concrete floor or non-combustible base. | □ | □ | □ | |
| 7.6 | Tag # is attached to the unit. | □ | □ | □ | |
| 7.7 | Service clearance is adequate for maintenance. | □ | □ | □ | |
| 7.8 | Proper earth ground is connected to green ground screw in panel. | □ | □ | □ | |
| 7.9 | Relief valve type, setting, and capacity are correct. | □ | □ | □ | |
| 7.10 | Gas lines are bled of air. | □ | □ | □ | |
| 7.11 | Draft hood or barometric damper is installed. | □ | □ | □ | |
| 7.12 | Vent stack is proper height and size. | □ | □ | □ | |
| 7.13 | Unrestricted vent cap on top to protect from weather and down drafts. | □ | □ | □ | |
| 7.14 | Gas inlet piping is properly installed. | □ | □ | □ | |
| 7.15 | Main and pilot gas valves are installed. | □ | □ | □ | |
| 7.16 | Hot water supply outlet is proper size. | □ | □ | □ | |
| 7.17 | Hot water return inlet is proper size. | □ | □ | □ | |
| 7.18 | Make up water supply has proper shut-off and back flow device. | □ | □ | □ | |
| 7.19 | Drain valve is installed. | □ | □ | □ |
| Print Name | Signature | Date |
|---|---|---|
| 7.20 | Temperature and pressure gauges are installed. | □ |
| 7.21 | High limit and operating controls are installed. | □ |
| 7.22 | Tube surfaces are inspected. | □ |
| 7.23 | Make-up water pressure regulator is installed. | □ |
| 7.24 | Expansion tank is installed. | □ |
| 7.25 | Pressure & temperature test ports are provided. | □ |
| 7.26 | Air separation device is properly installed. | □ |
| 7.27 | Pump(s) are installed. | □ |
| 7.28 | Pot feeder is installed. | □ |
| 7.29 | System has been cleaned and treated. | □ |
| 7.30 | Isolation valves are installed. | □ |
| 7.31 | Water treatment is installed. | □ |
| 7.32 | Steam check valves are installed. | □ |
| 7.33 | Steam traps are installed. | □ |
| 7.34 | Steam condensate is returned to steam make-up tank or sent to a tempering device before drain. | □ |
Section 8: Operational Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 8.2 | Unit vibration is acceptable. | $\Box$ | $\Box$ | $\Box$ | |
| 8.3 | Heating components perform per manufacturer's specification. | $\Box$ | $\Box$ | $\Box$ |
| Comments/ Observations | |
|---|---|
| Print Name | Signature | Date |
|---|---|---|
START-UP SHEET Boiler
| Step | Inspection Description | Yes | No | N/A | Performed By(Initials & Date) |
|---|---|---|---|---|---|
| 8.4 | Natural gas supply pressure is at manufacturer's specification. | □ | □ | □ | |
| 8.5 | Manifold pressure is at manufacturer's specification. | □ | □ | □ | |
| 8.6 | Make sure thermostat is set. | □ | □ | □ | |
| 8.7 | Record start up operating parameters in the Supplementary Forms(FN 8.028.2 or FN 8.028.3). |
End of Section
Comments/ Observations
Comments/ ____
Performed By
(Therma)
Reviewed By
(Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|