8 035 1 start up sheet heat exchanger
START-UP SHEET Heat Exchanger
Job Name _____ Job Number _____
Job Address ____
Section 5: Equipment Description
| Spec. #: | Submittal #: | P&ID/Dwg #: |
|---|---|---|
| Area Served: | ||
| Primary Service Type: | ||
| Secondary Service Type: |
| Data | Design | Actual On Site |
|---|---|---|
| Unit Tag # | ||
| Manufacturer | ||
| Model # | ||
| Serial # |
Section 6: Equipment Pre-Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 6.2 | Nameplate data matches vendor specifications. | ☐ | ☐ | ☐ | |
| 6.3 | All parts are received. | ☐ | ☐ | ☐ | |
| 6.4 | No visible signs of damage, leak, or defective parts. | ☐ | ☐ | ☐ | |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection. | ☐ | ☐ | ☐ | |
| 6.6 | Operational and Maintenance(O&M) manual is available in the field. | ☐ | ☐ | ☐ | |
| 6.7 | Start-up technicians reviewed factory start-up procedures in the O&M manual. | ☐ | ☐ | ☐ |
Comments/ ____
Observations
Performed By (Therma)
Reviewed By (Owner/Representatives)
| Print Name | Signature | Date |
|---|---|---|
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 6.8 | Connections: Size and location match drawing. | □ | □ | □ | |
| 6.9 | Exchanger is clean and free of foreign matter. | □ | □ | □ |
Section 7: Installation Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 7.2 | Unit is installed per design. | ☐ | ☐ | ☐ | |
| 7.3 | Tag # is attached to the unit. | ☐ | ☐ | ☐ | |
| 7.4 | Service clearance is adequate for maintenance. | ☐ | ☐ | ☐ | |
| 7.5 | Orientation of inlet and outlet thermometers and pressure gauges are correct. | ☐ | ☐ | ☐ | |
| 7.6 | Primary media relief valve is installed. | ☐ | ☐ | ☐ | |
| 7.7 | Secondary media relief valve is installed. | ☐ | ☐ | ☐ | |
| 7.8 | Drains and air bleeds are installed. | ☐ | ☐ | ☐ | |
| 7.9 | Sanitary design unit is completely drainable. | ☐ | ☐ | ☐ | |
| 7.10 | Insulation is per specification. | ☐ | ☐ | ☐ | |
| 7.11 | Bolts and studs are accessible. | ☐ | ☐ | ☐ | |
| 7.12 | Clamps, flanges and bolts are tight. | ☐ | ☐ | ☐ | |
| 7.13 | Unit has been leak tested. | ☐ | ☐ | ☐ |
Section 8: Operational Inspection
| Step | Inspection Description | Yes | No | N/A | Performed By (Initials & Date) |
|---|---|---|---|---|---|
| 8.2 | Record the operating parameters. |
| Comments/ Observations |
|---|
| Print Name | Signature | Date |
|---|---|---|
START-UP SHEET Heat Exchanger
Record Start Up Operating Parameters
| Data | Design | Actual On Site |
|---|---|---|
| Primary Type Data: | ||
| Outlet Pressure(PSI) | ||
| Outlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$ | ||
| Inlet Pressure(PSI) | ||
| Inlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$ | ||
| Secondary Type Data: | ||
| Outlet Pressure(PSI) | ||
| Outlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$ | ||
| Inlet Pressure(PSI) | ||
| Inlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$ |
End of Section
Comments/ Observations
Comments/ ____
| Print Name | Signature | Date |
|---|---|---|