8 035 1 start up sheet heat exchanger

START-UP SHEET Heat Exchanger

Job Name _____ Job Number _____

Job Address ____

Section 5: Equipment Description

Spec. #: Submittal #: P&ID/Dwg #:
Area Served:
Primary Service Type:
Secondary Service Type:
Data Design Actual On Site
Unit Tag #
Manufacturer
Model #
Serial #

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By (Initials & Date)
6.2 Nameplate data matches vendor specifications. ☐ ☐ ☐
6.3 All parts are received. ☐ ☐ ☐
6.4 No visible signs of damage, leak, or defective parts. ☐ ☐ ☐
6.5 Verify electrical service for correct voltage, current and thermal overload protection. ☐ ☐ ☐
6.6 Operational and Maintenance(O&M) manual is available in the field. ☐ ☐ ☐
6.7 Start-up technicians reviewed factory start-up procedures in the O&M manual. ☐ ☐ ☐

Comments/ ____

Observations

Performed By (Therma)

Reviewed By (Owner/Representatives)

Print Name Signature Date

Step Inspection Description Yes No N/A Performed By (Initials & Date)
6.8 Connections: Size and location match drawing. □ □ □
6.9 Exchanger is clean and free of foreign matter. □ □ □

Section 7: Installation Inspection

Step Inspection Description Yes No N/A Performed By (Initials & Date)
7.2 Unit is installed per design. ☐ ☐ ☐
7.3 Tag # is attached to the unit. ☐ ☐ ☐
7.4 Service clearance is adequate for maintenance. ☐ ☐ ☐
7.5 Orientation of inlet and outlet thermometers and pressure gauges are correct. ☐ ☐ ☐
7.6 Primary media relief valve is installed. ☐ ☐ ☐
7.7 Secondary media relief valve is installed. ☐ ☐ ☐
7.8 Drains and air bleeds are installed. ☐ ☐ ☐
7.9 Sanitary design unit is completely drainable. ☐ ☐ ☐
7.10 Insulation is per specification. ☐ ☐ ☐
7.11 Bolts and studs are accessible. ☐ ☐ ☐
7.12 Clamps, flanges and bolts are tight. ☐ ☐ ☐
7.13 Unit has been leak tested. ☐ ☐ ☐

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By (Initials & Date)
8.2 Record the operating parameters.
Comments/ Observations
Print Name Signature Date

START-UP SHEET Heat Exchanger

Record Start Up Operating Parameters

Data Design Actual On Site
Primary Type Data:
Outlet Pressure(PSI)
Outlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$
Inlet Pressure(PSI)
Inlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$
Secondary Type Data:
Outlet Pressure(PSI)
Outlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$
Inlet Pressure(PSI)
Inlet Temp. $ ^{\circ} \mathrm{F}(^{\circ} \mathrm{C})$

End of Section

Comments/ Observations

Comments/ ____

Print Name Signature Date