# START-UP SHEET Fan

## START-UP SHEET 1601 Las Plumas Ave.
## Fan Ph: (408) 347-3400

**Job Name Job Number**

**Job Address**

## Section 5: Equipment Description

| Spec. #: | Submittal #: | P&amp;ID / Dwg #: |
| --- | --- | --- |
| Area Served: |  |  |

**Service Type:  Supply Return  Exhaust Other:**

| Data | Design | Actual On Site |
| --- | --- | --- |
| Unit Tag # |  |  |
| Manufacturer |  |  |
| Model # |  |  |
| Serial # |  |  |

| Belt Description |  |  |  |
| --- | --- | --- | --- |
| Size&amp;Quantity |  |  |  |

**Section 6: Equipment Pre-Installation Inspection**

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 6.2 | Nameplate data matches vendor specifications. | □ | □ | □ |  |
| 6.3 | All parts are received. | □ | □ | □ |  |
| 6.4 | No visible signs of damage, leak, or defective parts. | □ | □ | □ |  |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection. | □ | □ | □ |  |
| 6.6 | Operational and Maintenance(O&amp;M) manual is available in the field. | □ | □ | □ |  |

**Comments/**

**Observations**

**Performed By**

**(Therma)**

**Reviewed By**

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

**(Owner/Representatives)**

---

# START-UP SHEET Fan

## START-UP SHEET 1601 Las Plumas Ave.
## Fan Ph: (408) 347-3400

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 6.7 | Start-up technicians have reviewed factory start-up procedures in the O&amp;M manual. | □ | □ | □ |  |
| 6.8 | If Therma provided a Variable Frequency Drive(VFD) that is controlling the fan, complete FN8.029.1 VFD start up form. |  |  |  |  |

**Section 7: Installation Inspection**

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 7.2 | Unit is installed level. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.3 | Tag # is attached to the unit. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.4 | Service clearance is adequate for maintenance. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.5 | All access panels and covers are in place. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.6 | Vibration isolators are installed and adjusted. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.7 | Ductwork and flex connections are connected and sealed. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.8 | Fan drive belt tension is correct. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.9 | Sheaves are aligned. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.10 | Fan hub, sheaves and bearing setscrews are tight. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.11 | Motor and blower bearings are lubricated. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.12 | Electrical connections are secure. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.13 | Fan shaft bearings angular alignment is correct and bolts are tight. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 7.14 | Auxiliary drain pan is installed and its connections are piped. | $\\Box$ | $\\Box$ | $\\Box$ |  |

**Comments/**

**Observations**

**Performed By** 
**(Therma)**

**Reviewed By**

**(Owner/Representatives)**

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

---

# START-UP SHEET Fan

## START-UP SHEET 1601 Las Plumas Ave.
## Fan Ph: (408) 347-3400

**Section 8: Operational Inspection**

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 8.2 | Unit vibration is acceptable. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.3 | Fan rotation is correct. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.4 | Supply, return or exhaust air dampers are functional. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.5 | Fire dampers are functional. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.6 | Supply, return and outside air dampers are functional. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.7 | Smoke detector is tested and is able to shut the unit down. | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.8 | Make sure thermostat is set | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.9 | Make sure time clock is set | $\\Box$ | $\\Box$ | $\\Box$ |  |
| 8.10 | Record start up operating parameters in the Supplementary Forms(FN 8.028.2 or FN 8.028.3). | $\\Box$ | $\\Box$ | $\\Box$ |  |

**Record Start Up Operating Parameters**

| Data | Design | Actual On Site |  |  |
| --- | --- | --- | --- | --- |
| Unit Voltage |  |  |  |  |
| Current |  |  |  |  |
| Phase |  |  |  |  |

**End of Section**

**Comments/**

**Observations**

|  | Print Name | Signature | Date |
| --- | --- | --- | --- |
| Performed By (Therma) |  |  |  |
| Reviewed By (Owner/Representatives) |  |  |  |