Start up - Fan

START-UP SHEET Fan

START-UP SHEET 1601 Las Plumas Ave.

Fan Ph: (408) 347-3400

Job Name Job Number

Job Address

Section 5: Equipment Description

Spec. #: Submittal #: P&ID / Dwg #:
Area Served:

Service Type: Supply Return Exhaust Other:

Data Design Actual On Site
Unit Tag #
Manufacturer
Model #
Serial #
Belt Description
Size&Quantity

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.2 Nameplate data matches vendor specifications. □ □ □
6.3 All parts are received. □ □ □
6.4 No visible signs of damage, leak, or defective parts. □ □ □
6.5 Verify electrical service for correct voltage, current and thermal overload protection. □ □ □
6.6 Operational and Maintenance(O&M) manual is available in the field. □ □ □

Comments/

Observations

Performed By

(Therma)

Reviewed By

Print Name Signature Date

(Owner/Representatives)


START-UP SHEET Fan

START-UP SHEET 1601 Las Plumas Ave.

Fan Ph: (408) 347-3400

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.7 Start-up technicians have reviewed factory start-up procedures in the O&M manual. □ □ □
6.8 If Therma provided a Variable Frequency Drive(VFD) that is controlling the fan, complete FN8.029.1 VFD start up form.

Section 7: Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.2 Unit is installed level. $\Box$ $\Box$ $\Box$
7.3 Tag # is attached to the unit. $\Box$ $\Box$ $\Box$
7.4 Service clearance is adequate for maintenance. $\Box$ $\Box$ $\Box$
7.5 All access panels and covers are in place. $\Box$ $\Box$ $\Box$
7.6 Vibration isolators are installed and adjusted. $\Box$ $\Box$ $\Box$
7.7 Ductwork and flex connections are connected and sealed. $\Box$ $\Box$ $\Box$
7.8 Fan drive belt tension is correct. $\Box$ $\Box$ $\Box$
7.9 Sheaves are aligned. $\Box$ $\Box$ $\Box$
7.10 Fan hub, sheaves and bearing setscrews are tight. $\Box$ $\Box$ $\Box$
7.11 Motor and blower bearings are lubricated. $\Box$ $\Box$ $\Box$
7.12 Electrical connections are secure. $\Box$ $\Box$ $\Box$
7.13 Fan shaft bearings angular alignment is correct and bolts are tight. $\Box$ $\Box$ $\Box$
7.14 Auxiliary drain pan is installed and its connections are piped. $\Box$ $\Box$ $\Box$

Comments/

Observations

Performed By (Therma)

Reviewed By

(Owner/Representatives)

Print Name Signature Date

START-UP SHEET Fan

START-UP SHEET 1601 Las Plumas Ave.

Fan Ph: (408) 347-3400

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
8.2 Unit vibration is acceptable. $\Box$ $\Box$ $\Box$
8.3 Fan rotation is correct. $\Box$ $\Box$ $\Box$
8.4 Supply, return or exhaust air dampers are functional. $\Box$ $\Box$ $\Box$
8.5 Fire dampers are functional. $\Box$ $\Box$ $\Box$
8.6 Supply, return and outside air dampers are functional. $\Box$ $\Box$ $\Box$
8.7 Smoke detector is tested and is able to shut the unit down. $\Box$ $\Box$ $\Box$
8.8 Make sure thermostat is set $\Box$ $\Box$ $\Box$
8.9 Make sure time clock is set $\Box$ $\Box$ $\Box$
8.10 Record start up operating parameters in the Supplementary Forms(FN 8.028.2 or FN 8.028.3). $\Box$ $\Box$ $\Box$

Record Start Up Operating Parameters

Data Design Actual On Site
Unit Voltage
Current
Phase

End of Section

Comments/

Observations

Print Name Signature Date
Performed By (Therma)
Reviewed By (Owner/Representatives)