# START-UP SHEET Condensing Unit

Job Name ____ Job Number ____

Job Address ____

## Section 5: Equipment Description

| Spec. #: | Submittal #: | P&amp;ID/Dwg #: |
| --- | --- | --- |
| Area Served: |  |  |

| Data | Design | Actual On Site |
| --- | --- | --- |
| Unit Tag # |  |  |
| Manufacturer |  |  |
| Model # |  |  |
| Serial # |  |  |
| Refrigerant Type |  |  |
| Refrigerant Quantity(lbs.) |  |  |

## Section 6: Equipment Pre-Installation Inspection

| Step | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 6.2 | Nameplate data matches vendor specifications. | □ | ⊗ | □ |  |
| 6.3 | All parts are received. | □ | □ | □ |  |
| 6.4 | No visible signs of damage, leak, or defective parts. | □ | □ | □ |  |
| 6.5 | Verify electrical service for correct voltage, current and thermal overload protection. | □ | □ | □ |  |
| 6.6 | Operational and Maintenance(O&amp;M) manual is available in field. | □ | □ | □ |  |
| 6.7 | Start-up technicians have reviewed factory start-up procedures in O&amp;M manual. | □ | □ | □ |  |

Comments/ Observations

---

Performed (Therma)

By

Reviewed By (Owner/Representatives)

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

---

## Section 7: Installation Inspection

| ID | Inspection Description | Yes | No | N/A | Performed By (Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 7.2 | Unit is installed level. | □ | □ | □ |  |
| 7.3 | Tag # is attached to the unit. | □ | □ | □ |  |
| 7.4 | Service clearance is adequate for maintenance. | □ | □ | □ |  |
| 7.5 | Vibration isolators are installed and adjusted. | □ | □ | □ |  |
| 7.6 | All compressor shipping braces and compressor rail isolator sleeves are removed. | □ | □ | □ |  |
| 7.7 | Compressor oil level is within manufacturer’s specification. | □ | □ | □ |  |
| 7.8 | Liquid line drier is installed properly. | □ | □ | □ |  |
| 7.9 | Suction line(s) is properly sized and installed. | □ | □ | □ |  |
| 7.10 | Liquid line(s) and Hot Gas Bypass line(s) is sized and installed. | □ | □ | □ |  |
| 7.11 | Suction and Hot Gas Bypass line(s) are insulated. | □ | □ | □ |  |
| 7.12 | All condenser fan setscrews are tight. | □ | □ | □ |  |
| 7.13 | Coils are clean &amp; fins are straight. | □ | □ | □ |  |
| 7.14 | Low ambient control is installed. | □ | □ | □ |  |
| 7.15 | All bearings are lubricated. | □ | □ | □ |  |
| 7.16 | Piping has undergone pressure test | □ | □ | □ |  |
| 7.17 | Piping is clamped and isolated. | □ | □ | □ |  |
| 7.18 | Piping is labeled. | □ | □ | □ |  |
| 7.19 | Crankcase heaters are installed. | □ | □ | □ |  |
| 7.20 | Electrical connections are secure. | □ | □ | □ |  |
| 7.21 | All access panels and covers are in place. | □ | □ | □ |  |

Performed By (Therma)

Reviewed By (Owner/Representatives)

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |

---

## Section 8: Operational Inspection

| ID | Inspection Description | Yes | No | N/A | Performed By(Initials &amp; Date) |
| --- | --- | --- | --- | --- | --- |
| 8.2 | Unit vibration is acceptable. | $$ | $$ | $$ |  |
| 8.3 | Fan rotation is correct. | $$ | $$ | $$ |  |
| 8.4 | Crankcase heaters are functional. | $$ | $$ | $$ |  |
| 8.5 | Cooling components perform per manufacturer&#x27;s specifications. | $$ | $$ | $$ |  |
| 8.6 | Make sure thermostat is set. | $$ | $$ | $$ |  |
| 8.7 | Record start up operating parameters in the Supplementary Forms(FN 8.028.2 or FN 8.028.3). |  |  |  |  |

End of Section

Comments/

Observations

Performed By

(Therma)

Reviewed By

| Print Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |