Start up - Air Handling Unit

START-UP SHEET

Air Handling Unit

Job Name Job Number
Job Address

Section 5: Equipment Description

Spec. #: Submittal #: P&ID / Dwg #:
Area Served:
Data Design Actual On Site
Unit Tag #
Manufacturer
Model #
Serial #

Record filter information below:

Filter Description Pre-Filter Bag Filter Final Filter
Type
Size&Quantity
Size&Quantity

| Belt Description | | | | | --- | --- | --- | | Size&Quantity | | | |

Section 6: Equipment Pre-Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.2 Nameplate data matches vendor specifications. □ □ □
6.3 All parts are received. □ □ □
6.4 No visible signs of damage, leak, or defective parts. □ □ □

Comments/

Observations
Performed By
(Therma)
Reviewed By

Print Name Signature Date

(Owner/Representatives)


Step Inspection Description Yes No N/A Performed By(Initials & Date)
6.5 Verify electrical service for correct voltage, current and thermal overload protection. □ □ □
6.6 Operational and Maintenance(O&M) manual is available in the field. □ □ □
6.7 Start-up technicians reviewed factory start-up procedures in the O&M manual. □ □ □
6.8 If Therma provided Variable Frequency Drives(VFDs) that are controlling the fans, complete FN-8029.1 VFD start up form(s).
6.9 If Therma provided smoke fire dampers use form SFT-Test □ □ □

Section 7: Installation Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
7.2 Unit is installed level. $
7.3 Tag # is attached to the unit. $
7.4 Service clearance is adequate for maintenance. $
7.5 Roof curb is installed to mate with the unit. $
7.6 All access panels and covers are in place. $
7.7 Vibration isolators are installed and adjusted. $
7.8 Ductwork and flex connections are connected and sealed. $
7.9 Economizer or outside air damper is installed. $
7.10 All filters are in place and positioned properly. $
7.11 Pressure and temperature taps are installed. $
7.12 Heating and cooling coil valves are mounted with actuator. $
7.13 Condensate drain and trap are installed. $
7.14 Auxiliary drain pan is installed and its connections are piped. $
7.15 All piping, coils,and valves are in place without leaks. $
7.16 Shipping blocks and materials are removed from fan section. $
7.17 Each fan drive belt tension is correct. $
7.18 Sheaves are aligned. $
7.19 Fan hub,sheaves,and bearing set-screws are tight. $
7.20 Smoke detector is installed. $
7.21 Motor and blower bearings are lubricated. $
7.22 Electrical connections are secure. $
7.23 Thermostat is installed. $
7.24 Time clock is installed. $
7.25 Fan shaft bearings angular alignment is correct and bolts are tight. $
7.26 Coils are clean fins are straight. $

| | Print Name | Signature | Date | | --- | --- | --- | | Performed By(Therma) | | | | | Reviewed By(Owner/Representatives) | | | |


START-UP SHEET

Air Handling Unit

Section 8: Operational Inspection

Step Inspection Description Yes No N/A Performed By(Initials & Date)
8.2 Unit vibration is acceptable. $
8.3 Each fan rotation is correct. $
8.4 Heating water and cooling water control valves are functional. $
8.5 Fire dampers are functional and open. $
8.6 Supply, return and outside air dampers are functional. $
8.7 Smoke detector is tested and is able to shut the unit down. $
8.8 Make sure thermostat is set $
8.9 Make sure time clock is set $
8.10 Record start up operating parameters in the Supplementary Forms(FN 8.028.2 or FN 8.028.3).

End of Section

Comments/

Observations

| | Print Name | Signature | Date | | --- | --- | --- | | Performed By(Therma) | | | | | Reviewed By(Owner/Representatives) | | | |