6 026 1 cycle purge test log

#: FN 6.026.1 Rev. 0

Foreperson’s Cycle Purge Instruction Set
Project Site/Name:

Project Site/Name: Date:(DDMMMYYYY)
Project Number: Purge Test #:
Building #: Room #(s):
System Name: Purge Medium:
System Description: Medium Source Lot/Batch#:
Line# (s): Medium Source Type:
Drawings, PID/Spool #(s): Spools/PID attached Locations Purged / Valve Tag #’s / Quantity: □Yes □No
Clean Wiper Test Required? □Yes □No
Owner, GC, Trades, Others notified of plan? □Yes □No
Pressure Test Verification Prior to Cycle Purge? Foreperson’s Initials & Date // (foreperson) (DDMMMYYYY)

Purging Report

Are all POU valves correctly labeled?

Are all POU valves correctly labeled? □Yes □No
Was each valve opened min 5 seconds per cycle? □Yes □No
Was each valve purged a minimum of 3 cycles? □Yes □No
Clean wiper test performed & passed? □Yes □No □N/A
Non-conformance with labeling or particulate? □Yes □No
If non-conformance, note details here:
Purge Team Leader Print Name: //(signature)(DDMMMYYYY)

Foreperson’s Acceptance

Print Name: /
(signature) (DDMMYYYY)