# CLEANING AND FLUSHING LOG

Project: ____

Test No.: ____

Project No.: ____

Date of Test: ____

## Brief Description of Test and Boundaries

| Test Medium:         | Drawing / Spool #:    |
| ------------------- | -------------------- |
| System:            | Line #:               |
| Pipe Size(Inch):   | Minimum flowrate:     |
| Equipment Included: | Temporary equipment such as piping, hose, pumps, tanks, etc. |

Has each system been completely pressure leak tested?

Yes  No

## Test Results

| Start Time | End Time | Duration Time(*) | Notes |
| ---------- | -------- | ---------------- | ----- |
|            |          |                  |       |
|            |          |                  |       |
|            |          |                  |       |

Note: * If system is purged with nitrogen, air, etc. keep purging until attached to a clean white cloth at the end of test drop. If the system is cleaned & flushed with chemicals, the duration shall follow chemical vendor's recommendation.

DCR 05002

FN 6.006.1 (Rev. 0)